Hitachi Zosen Inova to build a CHF 330 million multifuel generation plant in Ferrybridge, Yorkshire (UK)
The client for the new plant is Ferrybridge Multifuel Energy Ltd, a joint venture between SSE plc and Wheelabrator Technologies Inc. SSE is one of the leading energy utilities in the UK, while Wheelabrator Technologies is a US international owner and operator of energy-from-waste plants. Hitachi Zosen Inova was chosen for the construction of the facility in Ferrybridge thanks to its comprehensive experience and references from comparable turn key projects.
The new plant, which has received Section 36 consent by the Department of Energy & Cli-mate Change following intensive environmental impact assessments, will be built on the site of the existing coal-fired power station in Ferrybridge. Construction will start in late 2012, and will be concluded in early 2015.
The multifuel facility will primarily be supplied with fuel from the Yorkshire region, and in par-ticular from the local councils in Barnsley, Rotherham, and Doncaster. Due to pioneering technology, so-called multifuel firing combustion plants can process various types of fuel simultaneously and in Ferrybridge the design allows for up to 42 tonness per hour to be pro-cessed in each of the two process lines. The energy generated by the 68 MW plant will be fed into the grid in the form of electricity, with an option to export heat if there is a local de-mand.
SSE's Managing Director of Generation, Paul Smith, said:
«The transactions that make up this project represent a strong partnership between four major players in the multifuel sector, who are committed to making a serious level of investment in this technology. Between them the companies involved have extensive experience in sourcing and processing waste, constructing and commissioning multifuel technologies, and operating generation plant. This partnership creates a great platform to develop multi-fuel technology in future.»
Tony McShane, Project Director at HZI said:
«We are very proud that SSE / Wheelabrator have awarded this prestigious project to Hitachi Zosen Inova. We believe that our continuous investment in enhanced technology coupled with our track record of successful turn-key project delivery were major factors in the deci-sion making of SSE and Wheelabrator.»
Managing Director of Wheelabrator Technologies in the UK, Gary Aguinaga, said:
«Wheelabrator is delighted to reach contractual close with SSE to design, build and operate a modern multifuel facility at the Ferrybridge site in West Yorkshire. We are committed to forming strong partnerships as we continue to expand our operations across the UK and Europe. Through the Multifuel Energy joint venture, we are combining our expertise and ex-perience to deliver a state-of -the-art facility which will provide significant amounts of clean energy.»
The contract to build the modern multifuel plant marks Hitachi Zosen Inova's fifth project in the UK. Plants in Cleveland, Newhaven and Riverside, built by the company, in some cases under its former name of Von Roll Inova, are already in operation, and the extension of the Cleveland facility will be completed in 2013. The Swiss leader in EfW technology has thus displayed impressive continuity in its ability to deliver innovation and successfully tap into markets under the new ownership of the technology group Hitachi Zosen Corporation.